Back to Planning Applications
PA/2020/1908
Application Details
Reference
PA/2020/1908
Proposed Development
Planning permission for the construction and operation of a compound consisting of 7 x gas generators, security fencing with ancillary structures & associated works ADDITIONAL SUPPORTING INFORMATION
Date Valid
30 November 2020
Decision
Approve with Conditions
Decision Date
18 March 2021
Consultation End Date
7 January 2021
Location
Site Location
Hornsea 1 Limited, Access Roads To Power Stations Off Chase Hill Road, North Killingholme, DN40 3LU
Parish
North Killingholme
Ward
Ferry
Grid Reference
515063, 419317
Case Officer
Officer Name
Scott Jackson
Contact Number
01724 297000
Contact Email
planning@northlincs.gov.uk
Related Documents
Document Type | Description | Date | |
---|---|---|---|
Application Form | Download | 15 December 2020 | |
Decision Notice | Download | 18 March 2021 | |
Delegated Assessment | Download | 18 March 2021 | |
Drawing | Proposed Site Plan 1 1000 | 15 December 2020 | |
Drawing | Proposed Site Plan 1 5000 | 15 December 2020 | |
Drawing | Proposed East & West Elevations | 15 December 2020 | |
Drawing | Proposed Site Plan 1 500 | 15 December 2020 | |
Drawing | Proposed North & South Elevations | 15 December 2020 | |
Drawing | Proposed Development Site Layout | 15 December 2020 | |
Supporting Document | Air Quality Assessment | 15 December 2020 | |
Supporting Document | Noise Assessment | 15 December 2020 | |
Supporting Document | Best Available Techniques Statement | 15 December 2020 | |
Supporting Document | Flood Risk Information | 15 December 2020 | |
Supporting Document | Supporting Statement | 15 December 2020 | |
Supporting Document | Indicative Design Drawing of DRE & Container | 15 December 2020 | |
Supporting Document | Photographs of Proposed Development Site | 15 December 2020 | |
Supporting Document | Air Quality Details | 18 February 2021 | |
Supporting Document | Gas Power Rating | 18 February 2021 | |
Supporting Document | Supporting Information | 18 February 2021 |
Application Comments
Type | Name | Date | |
---|---|---|---|
Consultation Reply | Environmental Protection | 4 February 2021 | |
Consultation Reply | Environmental Protection | 15 March 2021 | |
Consultation Reply | Environmental Protection | 8 February 2021 | |
Consultation Reply | Ecology | 22 January 2021 | |
Consultation Reply |
Highways
Highway Condition Codes |
12 January 2021 |
Submit a Comment
The consultation period for this application has now ended.