Back to Planning Applications
PA/2023/1935
Application Details
Reference
PA/2023/1935
Proposed Development
Planning permission for the installation of a gas pressure reduction metering station and associated fencing
Date Valid
15 January 2024
Decision
Approve with Conditions
Decision Date
26 April 2024
Consultation End Date
13 March 2024
Location
Site Location
Chimney 23m From B W S C G S Uk Ltd, Brigg Renewable Energy Plant 12m From Unnamed Road, Access Roads To Power Station, Scawby Brook, DN20 9LT
Parish
Scawby
Ward
Broughton and Scawby
Grid Reference
499021, 406009
Case Officer
Officer Name
Dean Watson
Contact Number
01724 297000
Contact Email
planning@northlincs.gov.uk
Related Documents
Document Type | Description | Date | |
---|---|---|---|
Application Form | Application Form | 15 January 2024 | |
Decision Notice | DN | 26 April 2024 | |
Delegated Assessment | DA | 26 April 2024 | |
Drawing | 1813-BRIG-ME-X-006-Cranked-Top Weldmesh Security Fence - Stand | 15 January 2024 | |
Drawing | 1813-BRIG-ME-X-007-Proposed Shingle Surface Detail | 15 January 2024 | |
Drawing | 1813-BRIG-ME-X-005-Proposed Intake Kiosk Detail | 15 January 2024 | |
Drawing | 1813-BRIG-ME-X-004-Proposed Control Room Kiosk Detail | 15 January 2024 | |
Drawing | 1813-BRIG-ME-X-003-Proposed Boiler House Kiosk Detail | 15 January 2024 | |
Drawing | 1813-BRIG-ME-X-002-Proposed Drainage Layout | 15 January 2024 | |
Drawing | 1813-BRIG-ME-X-001-Proposed Skid Elevations | 15 January 2024 | |
Drawing | 1813-BRIG-ME-X-000---Location Plan Mock-up (Based on Brigg Bess | 15 January 2024 | |
Drawing | 1813-BRIG-ME-L-002-A-A2 - Proposed Site Plan | 15 January 2024 | |
Drawing | 1813-BRIG-ME-L-001-0-General Arrangement - Equipment Removal | 15 January 2024 | |
General Documents | Composite Ecological Screening Report | 15 January 2024 | |
General Documents | HSL-240416140853-315-Final Outcome | 16 April 2024 | |
Supporting Document | Noise Impact Assessment Report | 2 February 2024 | |
Supporting Document | Supplementary Statement | 4 March 2024 | |
Supporting Document | Transport Technical Note | 15 January 2024 | |
Supporting Document | Covering Letter | 15 January 2024 | |
Supporting Document | Planning Statement | 15 January 2024 | |
Supporting Document | Flood Risk Assessment | 15 January 2024 | |
Supporting Document | Air Quality | 15 January 2024 | |
Supporting Document | Design & Access Statement | 15 January 2024 |
Application Comments
Type | Name | Date | |
---|---|---|---|
Consultation Reply | Environmental Protection | 7 March 2024 | |
Consultation Reply | Humberside Fire & Rescue | 16 January 2024 | |
Consultation Reply | Archaeology | 16 January 2024 | |
Consultation Reply | Health & Safety Executive | 17 January 2024 | |
Consultation Reply | Conservation | 22 January 2024 | |
Consultation Reply | Environment Agency | 22 March 2024 | |
Consultation Reply | Ancholme IDB | 25 January 2024 | |
Consultation Reply | Environment Agency | 26 January 2024 | |
Consultation Reply | Lead Local Flood Authority | 16 April 2024 | |
Consultation Reply |
Highways
Highway Condition Codes |
16 April 2024 | |
Consultation Reply | Scawby Parish Council | 12 February 2024 | |
Consultation Reply | Tracy Rokahr (Crime Reduction Officer, Humberside Police) New Pin | 5 February 2024 | |
Consultation Reply | Environmental Protection | 29 January 2024 |
Submit a Comment
The consultation period for this application has now ended.