Back to Planning Applications
PA/2023/1915
Application Details
Reference
PA/2023/1915
Proposed Development
Planning permission for the construction, operation (including maintenance) and reinstatement of land following use, of a temporary haul road, formed from a combination of existing roadways/hardstanding and new sections of road, and dismantling of warehouse canopy
Date Valid
18 December 2023
Decision
Consultation End Date
24 January 2024
Location
Site Location
Land at, and in the vicinity of, the existing Keadby Power Station, Trentside, Keadby, Scunthorpe, DN17 3EF
Parish
Keadby with Althorpe
Ward
Axholme North
Grid Reference
482856, 411639
Case Officer
Officer Name
Andrew Law
Contact Number
01724 297000
Contact Email
planning@northlincs.gov.uk
Related Documents
Document Type | Description | Date | |
---|---|---|---|
Application Form | Application Form | 18 December 2023 | |
Drawing | K3 HR Planning figures | 18 December 2023 | |
Drawing | K3 HR Engineering figs Proposed Haul Road Construction | 18 December 2023 | |
Drawing | K3 HR Engineering figs Route Detail Figures | 18 December 2023 | |
Drawing | Location Plan | 18 December 2023 | |
Drawing | K3 HR Engineering figs Longitudanal Sections | 18 December 2023 | |
Drawing | K3 HR Engineering figs OHL Crossing Plans | 18 December 2023 | |
Drawing | K3 HR Engineering figs Proposed Excavation below ground water level | 18 December 2023 | |
Supporting Document | K3 HR Ph1 Desk Based Assessment VP1 0 Part 4 | 18 December 2023 | |
Supporting Document | Environmental Statement Volume II consol | 18 December 2023 | |
Supporting Document | K3 HR Ph1 Desk Based Assessment VP1 0 Part 2 | 18 December 2023 | |
Supporting Document | K3 HR Ph1 Desk Based Assessment VP1 0 Part 3 | 18 December 2023 | |
Supporting Document | Environmental Statement Vol III Pt III App8A 8B | 18 December 2023 | |
Supporting Document | Outline Construction Environmental Management Plan | 18 December 2023 | |
Supporting Document | Water Framework Directive Screening Assessment | 18 December 2023 | |
Supporting Document | Environmental Statement Vol III Pt I App1A 2A | 18 December 2023 | |
Supporting Document | Environmental Statement Vol III Pt II App 7A 7C | 18 December 2023 | |
Supporting Document | Flood Risk Assessment | 18 December 2023 | |
Supporting Document | Habitat Regulations Assessment No Significant Effects Report | 18 December 2023 | |
Supporting Document | K3 HR Ph1 Desk Based Assessment VP1 0 Part 1 | 18 December 2023 | |
Supporting Document | Arboricultural Impact Assessment VP1 0 Part IIA Figures and Appendices | 18 December 2023 | |
Supporting Document | Arboricultural Impact Assessment VP1 0 Part IIB Figures and Appendices | 18 December 2023 | |
Supporting Document | Design and Access Statement | 18 December 2023 | |
Supporting Document | Environmental Statement Vol I Glossary and Table of Contents | 18 December 2023 | |
Supporting Document | Biodiversity Net Gain Plan Report VP1 0 | 18 December 2023 | |
Supporting Document | Cover Letter | 18 December 2023 | |
Supporting Document | Arboricultural Impact Assessment VP1 0 Part I Main Report | 18 December 2023 |
Application Comments
Type | Name | Date | |
---|---|---|---|
Consultation Reply |
Highways
Highway Condition Codes |
2 January 2024 | |
Consultation Reply | Archaeology | 8 January 2024 | |
Consultation Reply | IANN Water Level Management Board | 15 January 2024 | |
Consultation Reply | Natural England | 16 January 2024 | |
Consultation Reply | Environment Agency | 17 January 2024 | |
Consultation Reply | Historic England | 18 December 2023 | |
Consultation Reply | Canal & River Trust | 21 December 2023 | |
Consultation Reply | National Highways | 22 January 2024 | |
PD Ports | 24 January 2024 | ||
Web | Council | 18 January 2024 | |
Consultation Reply | Lead Local Flood Authority | 16 January 2024 | |
Consultation Reply | Environmental Protection | 29 December 2023 |