DISCO PA/2023/1458
Applications for discharge of conditions are not open to public consultation and the Local Planning Authority will only accept responses from persons/organisations that have been formally consulted and requested to provide comments.
Application Details
Reference
PA/2023/1458
Proposal
Application to discharge condition attached to planning permission PA/2020/1483 (condition 4)
Relating to
PA/2020/1483
Details of conditions to discharge
Historic Environment have been consulted on the submitted information and raise no objection. This condition is discharged on the basis of the details supplied in the document Archaeological Surveys.
Condition
Prior to commencement of development, the applicant, or their agents or successors in title, shall submit the following details to the local planning authority for their written approval:
(i) confirmation that a contract has been entered into with an archaeological contractor to undertake all stages of the archaeological mitigation programme
(ii) a timetable that provides sufficient notification and allowance of time to ensure the completion of the specified archaeological excavations and recording work ahead of construction commencing
(iii) details of the archaeological organisation proposed to implement the approved mitigation strategy; a list of all staff involved, including sub-contractors and specialists, their responsibilities and qualifications
(iv) arrangements to notify the North Lincolnshire Historic Environment Officer of the commencement of archaeological works at least 10 working days before commencement and a schedule of visits to monitor such works.
(i) confirmation that a contract has been entered into with an archaeological contractor to undertake all stages of the archaeological mitigation programme
(ii) a timetable that provides sufficient notification and allowance of time to ensure the completion of the specified archaeological excavations and recording work ahead of construction commencing
(iii) details of the archaeological organisation proposed to implement the approved mitigation strategy; a list of all staff involved, including sub-contractors and specialists, their responsibilities and qualifications
(iv) arrangements to notify the North Lincolnshire Historic Environment Officer of the commencement of archaeological works at least 10 working days before commencement and a schedule of visits to monitor such works.
Related Documents
Document Type | Description | Date | |
---|---|---|---|
Application Form | Application Form | 28 September 2023 | |
Decision Notice | Download | 7 March 2024 | |
Supporting Document | Archaeological surveys (condition 4) | 28 September 2023 |
Comments
Type | Name | Date | |
---|---|---|---|
Consultation Reply | Archaeology | 11 October 2023 |