Back to Planning Applications
DISCO PA/2020/1005
Applications for discharge of conditions are not open to public consultation and the Local Planning Authority will only accept responses from persons/organisations that have been formally consulted and requested to provide comments.
Application Details
Reference
PA/2020/1005
Proposal
Application to discharge conditions attached to planning permission PA/2020/273
Relating to
PA/2020/273
Details of conditions to discharge
The information received to discharge condition 3 is considered acceptable. The councils drainage team have reviewed the information and consider it to be acceptable. Condition 3 is therefore discharged.
Condition
 3. Â
No development shall take place until details showing an effective method of preventing surface water run-off from the highway onto the developed site is submitted to and approved in writing by the local planning authority. These facilities shall be implemented prior to the access and parking facilities being brought into use and thereafter so retained.
No development shall take place until details showing an effective method of preventing surface water run-off from the highway onto the developed site is submitted to and approved in writing by the local planning authority. These facilities shall be implemented prior to the access and parking facilities being brought into use and thereafter so retained.
The information received to discharge condition 4 is considered acceptable. The councils drainage team have reviewed the information and consider it to be acceptable. Condition 4 is therefore discharged.
Condition
4.
No development shall take place until details showing an effective method of preventing surface water run-off from hard paved areas within the site onto the highway have been approved in writing by the local planning authority. These facilities shall be implemented prior to the access and parking facilities being brought into use and thereafter so retained.
No development shall take place until details showing an effective method of preventing surface water run-off from hard paved areas within the site onto the highway have been approved in writing by the local planning authority. These facilities shall be implemented prior to the access and parking facilities being brought into use and thereafter so retained.
Related Documents
Document Type | Description | Date | |
---|---|---|---|
Application Form | Download | 4 August 2020 | |
Decision Notice | Download | 11 January 2022 | |
Drawing | Plan showing drainage channel | 4 August 2020 | |
Drawing | Site location | 4 August 2020 |
Comments
Type | Name | Date | |
---|---|---|---|
Consultation Reply | Drainage | 7 September 2020 |