Back to Planning Applications

PA/2023/58

Application Details

Reference PA/2023/58
Proposed Development Planning permission for a battery energy storage system and associated works
Date Valid 1 February 2023
Decision Approve with Conditions
Decision Date 12 January 2024
Consultation End Date 2 March 2023
Location
Site Location land north of Chapel Lane, Keadby
Grid Reference 483044, 411872
Case Officer
Officer Name Paul Skelton
Contact Number 01724 297000

Related Documents

Document Type Description Date  
Amended Documents Construction Traffic Management Plan 7 June 2023
Amended Documents Proposed Site Plan (RevO) 27 July 2023
Amended Documents Site Layout and Elevations (RevD) 27 July 2023
Amended Documents Proposed Parameters Plan (RevB) 27 July 2023
Application Form Download 1 February 2023
Committee Report Download 2 January 2024
Committee Report (Superseded) Download 28 November 2023
Decision Notice Download 12 January 2024
Drawing Existing Site Plan (RevA) 1 February 2023
Drawing Soft Landscape Plan 1 February 2023
Drawing General Arrangement Plan 1 February 2023
Drawing Location Plan (RevC) 1 February 2023
Drawing Soft Landscape Plan - UG 1635 LAN SL DRW 02 P10 10 August 2023
Drawing General Arrangement Plan - UG 1635 LAN GA DRW 01 Rev P09 10 August 2023
Drawing Photo Montage 23 August 2023
Drawing (Superseded) Proposed Parameters Plan (RevA) 1 February 2023
Drawing (Superseded) Site Layout and Elevations (RevB) 1 February 2023
Drawing (Superseded) Proposed Site Plan (RevN) 1 February 2023
General Documents 05 07 2023 E-mail Response 10 August 2023
Supporting Document Arboricultural Impact Assessment and Method Statement 1 February 2023
Supporting Document Statement of Community Involvement 1 February 2023
Supporting Document Flood Risk & Drainage Assessment 1 February 2023
Supporting Document Landscape & Visual Appraisal 1 February 2023
Supporting Document Planning Statement 1 February 2023
Supporting Document Noise Assessment 1 February 2023
Supporting Document Fencing Details 1 February 2023
Supporting Document Transport Statement 7 February 2023
Supporting Document Additional Information 7 September 2023
Supporting Document Tree Constraints Report 8 March 2023
Supporting Document Ecological Assessment v2 8 March 2023
Supporting Document Transport Statement July 2023 10 August 2023
Supporting Document Arboricultural Impact Assessment & Method Statement 80-857-R1-3 July 2023 10 August 2023
Supporting Document Battery Energy Storage Facility Noise Assessment 5396 Version 6 0 2023-07-10 10 August 2023
Supporting Document BESS as a Low Carbon Technology August 2023 10 August 2023
Supporting Document Biodiversity Metric 3 1 04 08 2023 10 August 2023
Supporting Document Construction Traffic Management Plan July 2023 10 August 2023
Supporting Document Landscape & Visual Appraisal August 2023 10 August 2023
Supporting Document Ecological Assessment Report 04 08 2023 10 August 2023
Supporting Document Flood Risk & Drainage Assessment Addendum 13 March 2023
Supporting Document Noise Assessment 14 November 2023
Supporting Document Response to NLC Comments 14 November 2023
Supporting Document Response Letter 14 November 2023
Supporting Document Noise Assessment 5396 Version 6 0 2023-07-10 18 October 2023
Supporting Document Technical Note 18 October 2023
Supporting Document Ecological Assessment Report 20 June 2023
Supporting Document Biodiversity Metric 20 June 2023
Supporting Document Response Letter from Applicant 23 October 2023
Supporting Document (Superseded) Construction Traffic Management Plan 7 February 2023

Application Comments

Type Name Date  
Consultation Reply Canal & River Trust 2 February 2023
Consultation Reply Environment Agency 4 April 2023
Consultation Reply PROW Officer 4 July 2023
Consultation Reply Environment Agency 7 February 2023
Consultation Reply Humberside Fire and Rescue 8 February 2023
Consultation Reply Canal & River Trust 11 August 2023
Consultation Reply Environment Agency 11 August 2023
Consultation Reply Humberside Fire & Rescue 15 August 2023
Consultation Reply Environmental Protection 16 November 2023
Consultation Reply Isle of Axholme and North Nottinghamshire Water Level Management Board 17 February 2023
Consultation Reply Environmental Protection 19 September 2023
Consultation Reply Ecology 21 June 2023
Consultation Reply Natural England 23 August 2023
Consultation Reply Environmental Protection 23 February 2023
Consultation Reply Natural England 24 August 2023
Consultation Reply Northern Powergrid 26 July 2023
Consultation Reply Natural England 27 June 2023
Consultation Reply Northern Powergrid 27 March 2023
Consultation Reply Highways
Highway Condition Codes
23 August 2023
Web Council 22 August 2023
Consultation Reply Lead Local Flood Authority 11 August 2023
Web carney 12 July 2023
Web carney 1 July 2023
Consultation Reply Highways
Highway Condition Codes
16 June 2023
Consultation Reply Highways
Highway Condition Codes
17 March 2023
Consultation Reply Lead Local Flood Authority 13 March 2023
Consultation Reply Tracy Rokahr (Crime Reduction Officer, Humberside Police) New Pin 1 March 2023
Web Parkin 28 February 2023
Web Chapman 27 February 2023
Web Chapman 25 February 2023
Web Laing 24 February 2023
Web Trundell 21 February 2023
Web Hamilton 21 February 2023
Web McCann 20 February 2023
Web Chapman 20 February 2023
Web Ashwell 20 February 2023
Web Whieldon 20 February 2023
Web Reynolds 20 February 2023
Web Amin 20 February 2023
Web Council 16 February 2023
Consultation Reply Tree Officer 10 February 2023

Submit a Comment