Back to Planning Applications
PA/2021/1525
Application Details
Reference
PA/2021/1525
Proposed Development
Planning permission to erect a monopole manufacturing facility
Date Valid
25 August 2021
Decision
Approve with Conditions
Decision Date
9 August 2022
Consultation End Date
6 July 2022
Location
Site Location
Land Off, Station Road, South Killingholme
Ward
Ferry
Grid Reference
517351, 418074
Case Officer
Officer Name
Andrew Law
Contact Number
01724 297000
Contact Email
planning@northlincs.gov.uk
Related Documents
Document Type | Description | Date | |
---|---|---|---|
Amended Documents | Biodiversity Net Gain Note | 14 April 2022 | |
Amended Documents | Updated Halton Marshes Wet Grassland Improvement Plan | 14 March 2022 | |
Amended Documents | Site Improvement Plan | 22 June 2022 | |
Amended Documents | Environmental Statement - Non-Technical Summary | 28 September 2021 | |
Amended Documents | Design and Access Statement | 28 September 2021 | |
Amended Documents | Environmental Statement - 3 Project Description Rev 1 | 28 September 2021 | |
Amended Documents | Environmental Statement - 8 Air Quality Rev 1 | 28 September 2021 | |
Amended Documents | Environmental Statement - 10 LVIA Rev 1 | 28 September 2021 | |
Amended Documents | Environmental Statement - 10 LVIA Figures Rev 1 | 28 September 2021 | |
Amended Documents | Monopole Factory Proposed Elevations | 28 September 2021 | |
Amended Documents | Monopole Factory Proposed Sections 1 of 2 | 28 September 2021 | |
Amended Documents | Monopole Factory Proposed Sections 2 of 2 | 28 September 2021 | |
Amended Documents | Planning Statement | 28 September 2021 | |
Application Form | Download | 31 August 2021 | |
Decision Notice | Download | 9 August 2022 | |
Delegated Assessment | Download | 9 August 2022 | |
Drawing | Proposed Cleaning Bay - Plans and Elevations | 31 August 2021 | |
Drawing | Proposed Factory - Elevations | 31 August 2021 | |
Drawing | Proposed Factory - Sections (1 of 2) | 31 August 2021 | |
Drawing | Proposed Factory - Sections (2 of 2) | 31 August 2021 | |
Drawing | Proposed Office - Ground Floor Plan | 31 August 2021 | |
Drawing | Proposed Office - First Floor Plan | 31 August 2021 | |
Drawing | Proposed Office - Roof Plan | 31 August 2021 | |
Drawing | Proposed Office - Elevations | 31 August 2021 | |
Drawing | Proposed Office - Sections (1 of 2) | 31 August 2021 | |
Drawing | Proposed Office - Sections (2 of 2) | 31 August 2021 | |
Drawing | Proposed Security Cabin - Plans and Elevations | 31 August 2021 | |
Drawing | Proposed Coating Repair Bays - Plans and Elevations | 31 August 2021 | |
Drawing | Indicative Site Plan - Final Levels | 31 August 2021 | |
Drawing | Indicative Site Plan - Drainage | 31 August 2021 | |
Drawing | Indicative Boundary Cross Sections | 31 August 2021 | |
Drawing | Indicative Lighting Columns Layout | 31 August 2021 | |
Drawing | Indicative Perimeter Fence Layout and Details | 31 August 2021 | |
Drawing | Planning Application Boundary | 31 August 2021 | |
Drawing | Topographical Survey | 31 August 2021 | |
Drawing | Proposed General Arrangement | 31 August 2021 | |
Drawing | Proposed Factory - Ground Floor Plan | 31 August 2021 | |
Drawing | Proposed Factory - First Floor Plan | 31 August 2021 | |
Drawing | Proposed Factory - Roof Plan | 31 August 2021 | |
Drawing | Site Location Plan | 31 August 2021 | |
General Documents | Agent | 8 August 2022 | |
Supporting Document | Response to National Highways Comments | 2 November 2021 | |
Supporting Document | Phase II Site Investigation | 6 September 2021 | |
Supporting Document | Schedule of application documents | 6 September 2021 | |
Supporting Document | Habitat Regulations Assessment | 22 July 2022 | |
Supporting Document | Appendix 8 1 Air Quality | 22 October 2021 | |
Supporting Document | Appendix 8 1 Air Quality | 22 October 2021 | |
Supporting Document | Figure 8 1 Traffic Receptors | 22 October 2021 | |
Supporting Document | Figure 8 1 Traffic Receptors | 22 October 2021 | |
Supporting Document | Annual Management/Monitoring Report (TEMMP) | 23 December 2021 | |
Supporting Document | Applicant Comments re Air Quality | 25 March 2022 | |
Supporting Document | Environmental Statement Non-Technical Summary | 31 August 2021 | |
Supporting Document | Protected Species Survey | 31 August 2021 | |
Supporting Document | Breeding Bird Survey | 31 August 2021 | |
Supporting Document | Waterbird Utilisation Report | 31 August 2021 | |
Supporting Document | Planning Statement | 31 August 2021 | |
Supporting Document | Habitats Regulations Assessment Reports Parts 1 and 2 | 31 August 2021 | |
Supporting Document | Design & Access Statement | 31 August 2021 | |
Supporting Document | Flood Risk Assessment | 31 August 2021 | |
Supporting Document | Environmental Statement | 31 August 2021 | |
Supporting Document | Transport Technical Notes | 31 August 2021 | |
Supporting Document (Superseded) | Updated Biodiversity Net Gain Provision | 23 December 2021 |
Application Comments
Type | Name | Date | |
---|---|---|---|
Consultation Reply | Exolum | 1 October 2021 | |
Consultation Reply | Hull City Council | 1 October 2021 | |
Consultation Reply | Anglian Water | 1 October 2021 | |
Consultation Reply | Natural England | 2 November 2021 | |
Consultation Reply | Historic England | 3 December 2021 | |
Consultation Reply | Environmental Protection (Noise) | 3 March 2022 | |
Consultation Reply | Lincolnshire Wildlife Trust | 3 November 2021 | |
Consultation Reply | Natural England | 4 August 2022 | |
Consultation Reply | Network Rail | 4 October 2021 | |
Consultation Reply | Natural England | 5 August 2022 | |
Consultation Reply | Defence Infrastructure Organisation | 6 October 2021 | |
Consultation Reply | National Grid | 7 September 2021 | |
Consultation Reply | Cadent Gas | 7 September 2021 | |
Consultation Reply | Phillips 66 | 10 November 2021 | |
Consultation Reply | DIO | 13 September 2021 | |
Consultation Reply | Natural England | 14 March 2022 | |
Consultation Reply | Archaeology | 15 November 2021 | |
Consultation Reply | Fisher German | 15 September 2021 | |
Consultation Reply | Exolum/Fisher German | 15 September 2021 | |
Consultation Reply | Fisher German Email | 16 September 2021 | |
Consultation Reply | Highways England | 17 December 2021 | |
Consultation Reply | Exolum/Fisher German | 17 September 2021 | |
Consultation Reply | Exolum/Fisher German | 17 September 2021 | |
Consultation Reply | Natural England | 19 May 2022 | |
Consultation Reply | Environmental Protection | 19 November 2021 | |
Consultation Reply | Exolum Pipeline Fisher German | 20 December 2021 | |
Consultation Reply | Internal Drainage Board | 20 January 2022 | |
Consultation Reply | Ecology | 22 April 2022 | |
Consultation Reply | National Highways | 23 November 2021 | |
Consultation Reply | National Highways | 23 November 2021 | |
Consultation Reply | Environment Agency | 28 September 2021 | |
Consultation Reply | Doncaster Airport | 28 September 2021 | |
Consultation Reply | Natural England | 29 April 2022 | |
Consultation Reply | Environment Agency | 30 September 2021 | |
Consultation Reply | Highways England | 30 September 2021 | |
Consultation Reply | Lincolnshire Wildlife Trust | 31 January 2022 | |
Applicant response to Phillips 66 consultation | 10 November 2021 | ||
Consultation Reply | Lead Local Flood Authority | 26 November 2021 | |
Consultation Reply | Natural England | 26 November 2021 | |
Consultation Reply | Environmental Protection | 23 November 2021 | |
Consultation Reply |
Highways
Highway Condition Codes |
4 November 2021 | |
Web | Gale | 3 November 2021 | |
Consultation Reply | NHS North Lincolnshire | 26 October 2021 | |
Consultation Reply | Tree Officer | 26 October 2021 | |
Consultation Reply | Tracy Rokahr (Community Safety, Humberside Police) | 15 October 2021 | |
Web | Limited | 14 October 2021 | |
Consultation Reply | Isle Of Axholme & North Nottinghamshire WLMB | 13 October 2021 | |
Web | RHA-Safeguarding | 8 October 2021 | |
Consultation Reply | Humberside Airport | 5 October 2021 | |
Web | Morgan | 3 October 2021 | |
Consultation Reply | Recycling | 29 September 2021 |
Submit a Comment
The consultation period for this application has now ended.
Related discharge of Conditions Applications
Reference | Proposal |
---|---|
PA/2023/1210 | Application to discharge conditions attached to planning permission PA/2021/1525 (condition 16) |