Back to Planning Applications
PA/2020/952
Application Details
Reference
PA/2020/952
Proposed Development
Planning permission for the creation of a biodiversity enhancement area (comprising the use of 70,000 cubic metres of excavated soil)
Date Valid
30 June 2020
Decision
Refuse
Decision Date
26 March 2021
Consultation End Date
4 September 2020
Location
Site Location
Keadby Power Station, Trent Side, Keadby, DN17 3EF
Grid Reference
482874, 411617
Case Officer
Officer Name
Scott Jackson
Contact Number
01724 297000
Contact Email
planning@northlincs.gov.uk
Related Documents
Document Type | Description | Date | |
---|---|---|---|
Application Form | Download | 11 August 2020 | |
Commitee Report | Download | 10 November 2020 | |
Decision Notice | Download | 26 March 2021 | |
Drawing | Site Layout Plan | 11 August 2020 | |
Drawing | Soil Storage Plan | 11 August 2020 | |
Drawing | Soil Storage Sections | 11 August 2020 | |
Drawing | Location Plan | 11 August 2020 | |
Supporting Document | Supporting Information | 8 February 2021 | |
Supporting Document | Environmental Site Assessment Report Pt 1 | 11 August 2020 | |
Supporting Document | Botanical Survey Report | 11 August 2020 | |
Supporting Document | Flood Risk Assessment | 11 August 2020 | |
Supporting Document | Planning Statement | 11 August 2020 | |
Supporting Document | Ecology Report | 11 August 2020 | |
Supporting Document | Habitat Survey | 11 August 2020 | |
Supporting Document | Covering Letter | 11 August 2020 | |
Supporting Document | Review of Options for Re-Use of Excavated Material Report | 11 August 2020 | |
Supporting Document | Environmental Site Assessment Report Pt 2 | 11 August 2020 | |
Supporting Document | Noise Note | 11 August 2020 | |
Supporting Document | Supporting Information | 13 October 2020 |
Application Comments
Type | Name | Date | |
---|---|---|---|
Consultation Reply | Environment Agency | 7 September 2020 | |
Consultation Reply | Natural England | 11 September 2020 | |
Consultation Reply | Archaeology | 13 August 2020 | |
Consultation Reply | Drainage | 23 November 2020 | |
Consultation Reply | Canal & River Trust | 27 August 2020 | |
Web | Carney | 30 September 2020 | |
Consultation Reply | Ecology | 23 September 2020 | |
Consultation Reply | Keadby with Althorpe Parish Council | 10 September 2020 | |
Consultation Reply | Lead Local Flood Authority | 4 September 2020 | |
Consultation Reply | Environmental Protection | 4 September 2020 | |
Consultation Reply | Network Rail | 3 September 2020 | |
Consultation Reply | Crowle and Ealand Town Council | 27 August 2020 | |
Consultation Reply | Environmental Protection | 24 August 2020 | |
Consultation Reply |
Highways
Highway Condition Codes |
11 August 2020 |
Submit a Comment
The consultation period for this application has now ended.