Planning permission to construct and refurbish pedestrian footpath and cycle path along Burringham Road (B1450) and to undertake highway improvements to existing roundabout to increase traffic capacity
Date Valid
4 September 2020
Decision
Approve with Conditions
Decision Date
6 May 2022
Consultation End Date
22 April 2021
Location
Site Location
Roundabout, Burringham Road, Scunthorpe
Parish
Ashby Parkland
Grid Reference
487369, 408372
Case Officer
Officer Name
Legacy User
Contact Number
01724 297000
Contact Email
planning@northlincs.gov.uk
Related Documents
Document Type | Description | Date | |
---|---|---|---|
Application Form | Download | 4 September 2020 | |
Decision Notice | Decision Notice | 9 May 2022 | |
Delegated Assessment | Delegated Assessment | 9 May 2022 | |
Drawing | Indicative Speed Limit | 4 September 2020 | |
Drawing | Burringham Road Site Boundary | 4 September 2020 | |
Drawing | Site Location Plan | 4 September 2020 | |
Drawing | Existing Vegetation | 4 September 2020 | |
Drawing | Site Clearance Plan | 4 September 2020 | |
Drawing | Highway Improvements | 4 September 2020 | |
Drawing | Proposed New Supplies - Sheet A | 29 October 2020 | |
Drawing | Proposed New Supplies - Sheet B | 29 October 2020 | |
Drawing | Proposed New Supplies - Sheet C | 29 October 2020 | |
Drawing | Proposed New Supplies - Sheet D | 29 October 2020 | |
Drawing | Burringham Road Proposed 2D Layout - Sheet A | 29 October 2020 | |
Drawing | Burringham Road Proposed 2D Layout - Sheet B | 29 October 2020 | |
Drawing | Burringham Road Proposed 2D Layout - Sheet C | 29 October 2020 | |
Drawing | Burringham Road Proposed 2D Layout - Sheet D | 29 October 2020 | |
Drawing | Burringham Road Drainage Manholes Schedule - Sheet 1 | 29 October 2020 | |
Drawing | Burringham Road Drainage Manholes Schedule - Sheet 2 | 29 October 2020 | |
Drawing | Earthworks - Excavations - Sheet A | 29 October 2020 | |
Drawing | Earthworks - Excavations - Sheet B | 29 October 2020 | |
Drawing | Earthworks - Excavations - Sheet C | 29 October 2020 | |
Drawing | Earthworks - Excavations - Sheet D | 29 October 2020 | |
Drawing | Earthworks - Pavement Foundations - Sheet A | 29 October 2020 | |
Drawing | Earthworks - Pavement Foundations - Sheet A | 29 October 2020 | |
Drawing | Earthworks - Pavement Foundations - Sheet B | 29 October 2020 | |
Drawing | Earthworks - Pavement Foundations - Sheet C | 29 October 2020 | |
Drawing | Earthworks - Pavement Foundations - Sheet D | 29 October 2020 | |
Drawing | Earthworks - Verge & Landscape Areas - Sheet A | 29 October 2020 | |
Drawing | Earthworks - Verge & Landscape Areas - Sheet B | 29 October 2020 | |
Drawing | Earthworks - Verge & Landscape Areas - Sheet C | 29 October 2020 | |
Drawing | Earthworks - Verge & Landscape Areas - Sheet D | 29 October 2020 | |
Drawing | Burringham Road Drainage - Flow Construction Details - Sheet 1 | 29 October 2020 | |
Drawing | Burringham Road Drainage - Flow Construction Details - Sheet 2 | 29 October 2020 | |
Drawing | Burringham Road Drainage - Flow Construction Details - Sheet 3 | 29 October 2020 | |
Drawing | Burringham Road Drainage - Flow Construction Details - Sheet 4 | 29 October 2020 | |
Drawing | Burringham Road Drainage - Flow Construction Details - Sheet 5 | 29 October 2020 | |
Drawing | Burringham Road Drainage - Standard Details - Sheet 1 | 29 October 2020 | |
Drawing | Burringham Road Drainage - Standard Details - Sheet 2 | 29 October 2020 | |
Drawing | Site Clearance - General - Sheet A | 29 October 2020 | |
Drawing | Site Clearance - General - Sheet B | 29 October 2020 | |
Drawing | Site Clearance - General - Sheet C | 29 October 2020 | |
Drawing | Site Clearance - General - Sheet D | 29 October 2020 | |
Drawing | Site Clearance - Drainage & Ducting - Sheet A | 29 October 2020 | |
Drawing | Site Clearance - Drainage & Ducting - Sheet B | 29 October 2020 | |
Drawing | Site Clearance - Drainage & Ducting - Sheet C | 29 October 2020 | |
Drawing | Site Clearance - Drainage & Ducting - Sheet D | 29 October 2020 | |
Drawing | Burringham Road - Drainage Layout - Sheet E | 29 October 2020 | |
Drawing | Burringham Road - Drainage Layout - Sheet A | 29 October 2020 | |
Drawing | Burringham Road - Drainage Layout - Sheet B | 29 October 2020 | |
Drawing | Burringham Road - Drainage Layout - Sheet C | 29 October 2020 | |
Drawing | Burringham Road - Drainage Layout - Sheet D | 29 October 2020 | |
Drawing | Burringham Road - Drainage Layout - Sheet F | 29 October 2020 | |
Drawing | Burringham Road - Drainage Layout - Sheet G | 29 October 2020 | |
Drawing | Burringham Road - Drainage Pipe Schedule | 29 October 2020 | |
Drawing | Pavement Areas - Sheet A | 29 October 2020 | |
Drawing | Pavement Areas - Sheet B | 29 October 2020 | |
Drawing | Proposed Traffic Signs Layout - Sheet C | 29 October 2020 | |
Drawing | Proposed Traffic Signs Layout - Sheet D | 29 October 2020 | |
Drawing | Traffic Sign Schedule | 29 October 2020 | |
Drawing | Road Markings - Sheet A | 29 October 2020 | |
Drawing | Road Markings - Sheet B | 29 October 2020 | |
Drawing | Road Markings - Sheet C | 29 October 2020 | |
Drawing | Road Markings - Sheet D | 29 October 2020 | |
Drawing | Proposed Lighting & Ducting - Sheet A | 29 October 2020 | |
Drawing | Proposed Lighting & Ducting - Sheet B | 29 October 2020 | |
Drawing | Proposed Lighting & Ducting - Sheet C | 29 October 2020 | |
Drawing | Proposed Lighting & Ducting - Sheet D | 29 October 2020 | |
Drawing | Pavement Areas - Sheet C | 29 October 2020 | |
Drawing | Pavement Areas - Sheet D | 29 October 2020 | |
Drawing | Pavements - Milling & Regulating - Sheet B | 29 October 2020 | |
Drawing | Pavements - Milling & Regulating - Sheet C | 29 October 2020 | |
Drawing | Pavements - Milling & Regulating - Sheet D | 29 October 2020 | |
Drawing | Kerbs & Footways - Sheet A | 29 October 2020 | |
Drawing | Kerbs & Footways - Sheet B | 29 October 2020 | |
Drawing | Kerbs & Footways - Sheet C | 29 October 2020 | |
Drawing | Kerbs & Footways - Sheet D | 29 October 2020 | |
Drawing | Pavements - Milling & Regulating - Sheet A | 29 October 2020 | |
Drawing | Site Location Plan | 29 October 2020 | |
Drawing | Existing Statutory Undertakers - Sheet A | 29 October 2020 | |
Drawing | Existing Statutory Undertakers - Sheet B | 29 October 2020 | |
Drawing | Existing Statutory Undertakers - Sheet C | 29 October 2020 | |
Drawing | Existing Statutory Undertakers - Sheet D | 29 October 2020 | |
Supporting Document | Planning Statement | 1 April 2021 | |
Supporting Document | Ecological Appraisal | 4 September 2020 | |
Supporting Document | Flood Risk Assessment | 4 September 2020 | |
Supporting Document | Appendices | 11 December 2020 | |
Supporting Document | Pre-Development Impact Assessment & Tree Report | 11 December 2020 | |
Supporting Document | Technical Note Appendix B - Existing Drainage Conditions & Indicative Site Materplan | 21 December 2020 | |
Supporting Document | Technical Note Appendix D - Proposed Drainage Layout Plans | 21 December 2020 | |
Supporting Document | Technical Note Appendix E - Proposed Drainage Design Calculations | 21 December 2020 | |
Supporting Document | Technical Note Appendix C - Proposed Drainage Catchment Areas | 21 December 2020 | |
Supporting Document | Technical Note Appendix A - Drainage Strategy Flood Risk Assessment | 21 December 2020 | |
Supporting Document | Technical Note | 21 December 2020 | |
Supporting Document | Earthworks Specification | 29 October 2020 |
Application Comments
Type | Name | Date | |
---|---|---|---|
Consultation Reply | Highways England | 2 November 2020 | |
Consultation Reply | Drainage | 6 January 2021 | |
Consultation Reply | Ecology | 7 July 2021 | |
Consultation Reply | National Grid | 9 September 2020 | |
Consultation Reply | Drainage | 13 October 2020 | |
Consultation Reply | Natural England | 14 September 2020 | |
Consultation Reply | Drainage | 16 September 2020 | |
Consultation Reply | Environment Agency | 18 November 2020 | |
Consultation Reply | Environment Agency | 23 September 2020 | |
Consultation Reply | Ecology | 28 September 2021 | |
Consultation Reply | Highways England | 29 September 2020 | |
Consultation Reply | Lead Local Flood Authority | 7 December 2020 | |
Consultation Reply | Ecology | 24 November 2020 | |
Consultation Reply | Natural England | 9 November 2020 | |
Consultation Reply | Archaeology | 5 November 2020 | |
Consultation Reply | Tree Officer | 12 October 2020 | |
Web | Rokahr | 22 September 2020 | |
Consultation Reply | National Grid Plant Protection | 16 September 2020 | |
Consultation Reply | Ashby Parkland Parish Council | 16 September 2020 | |
Consultation Reply | Archaeology | 15 September 2020 |